A case study on the stability of a big underground powerhouse cavern cut by an interlayer shear zone in the China Baihetan hydropower plant

Abstract

The big underground powerhouse cavern of the China Baihetan hydropower plant is 438 m long, 34 m wide, and 88.7 m high. It is cut by a weak interlayer shear zone and its high sidewall poses a huge stability problem. This paper reports our successful solution of this problem through numerical simulations and a replacement-tunnel scheme in the detailed design stage and close site monitoring in the excavation stage. Particularly, in the detail design stage, mechanical parameters of the shear zone were carefully determined through laboratory experiments and site tests. Then, deformation of the surrounding rocks and the shear zone under high in situ stress conditions was predicted using 3 Dimensional Distinct Element Code (3DEC). Subsequently, a replacement-tunnel scheme was proposed for the treatment on the shear zone to prevent severe unloading relaxation of surrounding rocks. In the construction period, excavation responses were closely monitored on deformations of surrounding rocks and the shear zone. The effect of local cracking in the replacement tunnels on sidewall stability was evaluated using the strength reduction method. These monitoring results were compared with the predicted numerical simulation in the detailed design stage. It is found that the shear zone greatly modified the deformation mode of the cavern surrounding rocks. Without any treatment, rock mass deformation on the downstream sidewall was larger than 125 mm and the shearing deformation of the shear zone was 60–70 mm. These preset replacement tunnels can reduce not only the unloading and relaxation of rock masses but also the maximum shearing deformation of the shear zone by 10–20 mm. The predictions by numerical simulation were in good agreement with the monitoring results. The proposed tunnel-replacement scheme can not only restrain the shear zone deformation but also enhance the safety of surrounding rocks and concrete tunnels. This design procedure offers a good reference for interaction between a big underground cavern and a weak layer zone in the future.

Highlights


  • A 9-year study on the deformation and stability problem of the large deep underground cavern in Baihetan power station was carried out.

  • The shearing deformation characteristics and creative replacement schemes of the interlayer shear zone were discussed.

  • The numerical simulations were verified by 2 years of monitoring data on the deformation of surrounding rocks and the interlayer shear zone.

  • The stability of replacement tunnels was evaluated using the strength reduction method.



1 INTRODUCTION

As the second largest hydropower station in China, Baihetan hydropower plant was built across Jinsha River in Southwest China. With a 289 m-high arch dam, it has the widest underground powerhouse cavern and the largest scale of underground openings in the world. It has an installed capacity of 16 million kW. All the hydraulic generator sets were put into use by December 2022. During its construction, this project faced three key problems in terms of rock mechanics: high in situ stress, shearing deformation of interlayer shear zones, and stability of columnar joints. These problems have attracted wide academic attention. Accordingly, a growing body of research has been conducted on this large underground project in the constitutive model of columnar basalt (Meng et al., 2020), mechanical anisotropy of columnar basalt (Jiang et al., 2014), in situ stress (Jiang et al., 2013), and cavern excavation and reinforcement (Hatzor et al., 2015; Jiang et al., 2010, Meng, Detournay, et al., 2016).

For stability analysis of underground openings, numerical simulation is very important (Mao & Bjørn, 2013; Whittaker & Frith, 1990). It is particularly useful in the detailed design stage for prediction or evaluation on the behaviors of underground caverns in the excavation process (Hatzor et al., 2015). Further, in situ monitoring data were also widely collected in the underground project for verification, prediction, and early warning (Høien et al., 2019; Kadir et al., 2020).

The strata at the left bank of Baihetan hydropower project are typical monoclinal structures. Interlayer shear zones, which are composed of weak tuff, are well developed between stratum layers. In this project, one large interlayer shear zone of thoroughly cuts through the underground powerhouse cavern at the left bank. How this interlayer shear zone affects the stability of the underground powerhouse cavern and how the interlayer shear zones are well treated under high field stress conditions are primary issues in such a large and important project. Similar cases have been studied by Jeon et al. (2004), Bakun-Mazor et al. (2009), and Wang et al. (2017), but they are all small caverns and weak zones. Also, Schubert et al. (2006) and Du et al. (2022) discussed support design and monitoring on tunneling in fault and weak fractured zones. Rahimi et al. (2021) proposed a new comprehensive underground excavation design methodology that has been successfully applied in two deep tunneling cases. A support system of rock bolts and two layers of shotcrete with welded wire mesh were used in shear zone areas around the powerhouse cavern in Guiarat, India (Bellapu et al., 2021). Spray of a thin layer of steel fiber-reinforced shotcrete, inclined rock bolt spray of shotcrete, and other treatments on interlayer shear zones have been recommended by Singh and Goel (2011). However, the Baihetan powerhouse cavern is 34 m wide, and is the widest in the world. It is 438 m long with a shear zone thoroughly cutting through. The largest burial depth of the cavern reaches up to 330 m. No existing cases can serve as references for such a big cavern. Also, the effects of the interlayer shear zone on the big cavern stability and control measures are still unclear.

This paper reports the long-term research progress toward a solution to the stability of this big cavern. Research lasted for 9 years, ranging from the detailed design stage (2011) to the construction stage (2020). This research covered a number of numerical simulations as prediction and their verification with in situ monitoring data. The control measures on shearing deformation of interlayer shear zones are fundamental to this large underground cavern. In 2011, during the detailed design stage, the properties of the interlayer shear zone C2 were investigated and its shearing deformation under high in situ stresses was predicted by using numerical analysis with 3DEC software (Itasca, 2010). Then, the interlayer shear zone replacement schemes were optimized in 2012. In the construction stage, the interlayer shear zone was replaced by concrete tunnels during 2014 and 2015, with the replacement-tunnel scheme proofed with numerical simulations again. The powerhouse cavern was excavated from 2014 till 2018, and the interlayer shear zone crossing the cavern was exposed during excavation in 2017. Finally, the previous numerical analysis in the detailed design stage was verified by the excavation responses of the powerhouse cavern and the in situ monitoring data. The shear zone replacement scheme was proven to be innovative and effective. In addition, the effects of local cracking in the replacement tunnels on the sidewall stability of the big underground cavern were explored using the strength reduction method. It is expected that the above procedure obtained in this case study offers a valuable reference for the interaction between a big underground cavern and a weak layer zone in future similar projects.

2 BRIEF DESCRIPTION OF THE BAIHETAN PROJECT

2.1 Underground caverns and geological conditions in this hydropower plant

The water division and power generation system in the Baihetan project include water intakes, pressure tunnels, powerhouse caverns, main transform tunnels, tailrace surge chambers, and tailrace tunnels. A part of the 3D geometry model of this project at the left bank is shown in Figure 1. The powerhouse cavern has the dimensions of 438.00 m (Long) × 34.00 m (Wide) × 88.70 m (Hide). The cavern axis orientation is N20° E.

      Details are in the caption following the image          
Figure 1      
Open in figure viewer         PowerPoint      
Draft of interlayer shear zone C       2 cutting the underground openings at the left bank.

The geological condition in the powerhouse cavern zone is complicated. The strata at the left bank are mainly P2β23, P2β24, and P2β31 basalt and breccia lava. The hard basalt is mainly composed of cryptocrystalline, porphyritic, and amygdaloidal basalt. The surrounding rock masses of the powerhouse are classified as grade III by the rock mass rating system (RMR) system. The burial depth of the powerhouse is 950–1050 m in the horizontal direction and 260–330 m in the vertical direction. The initial maximum principal stress is 19–23 MPa, and the measured maximum horizontal principal stress is 33.39 MPa. The angle between the initial maximum principal stress and the main axis of the powerhouse is 60°–70°.

2.2 Mechanical parameters of the interlayer shear zone

Interlayer shear zone C2 intersects the underground openings at the left bank (Figure 1). It is well developed between P2β24 and P2β31 basalt, with an average thickness of about 20 cm (Figure 2). It is composed of tuff, but also contains clay with rock fragments. Hence, its strength is low and can be easily softened by water. In addition, some small-scale faults and large fractures are distributed around the underground powerhouse at the right bank, such as f717, f718, f719, f720, f723, and LS3152. Three sets of joints are distributed around the underground powerhouse: (1) a strike of N30°–70° W, a SW tendency, and a dip angle of 65°–90°; (2) a strike of N50°–70° E, a SE tendency, and a dip angle of 50°–60°; and (3) a strike of N20°–50° E, a SE tendency and a dip angle of 10°–35°. The joint lengths are generally 2–5 m with spacing larger than 50 cm and 20–50 cm in local areas. The fracture planes are closed, straight, and rough.

      Details are in the caption following the image          
Figure 2      
Open in figure viewer         PowerPoint      
Cross section of the interlayer shear zone.

Strength parameters of the weak interlayer shear zone are critical to the stability analysis of the surrounding rocks. Five in situ direct shear tests were conducted and the results are shown in Figure 3. In order to avoid the size effect of the in situ experiments, numerical direct shear experiments were also conducted using 3DEC. The Coulomb-slip model in 3DEC was used to model opening, compressing, and shearing behaviors of structural planes (Itasca, 2010). The unloading relaxation of the interlayer shear zones is closely related to the thickness of the interlayer shear zone and the mechanical properties of its soft filling materials. In this study, both normal stiffness and shear stiffness of this interlayer shear zone were derived by the equivalent deformational response. Specifically, the normal stiffness Kn is 0.2 GPa/m and shear stiffness is 0.074 GPa/m.

      Details are in the caption following the image          
Figure 3      
Open in figure viewer         PowerPoint      
In situ direct shear test on the interlayer shear zone. (a) Sketch of the in situ test and (b) in situ test.

Figure 4 shows the comparison between numerical simulations and field experiments. As can be seen, they agree very well with each other. The parameters used in numerical simulations are listed in Tables 1 and 2. The strength parameters of the interlayer shear zone on a large scale were determined as follows: the cohesion was 0.09 MPa and the friction angle was 15.64°.

      Details are in the caption following the image          
Figure 4      
Open in figure viewer         PowerPoint      
Comparison between numerical simulations and in situ direct shear tests.
Table 1. Mechanical properties of rock masses.
Rock masses Modulus (GPa) Poisson's ratio Cohesion (MPa) Friction angle (°) Tensile strength (MPa)
Basalt 20.36 0.20 2.92 53.1 1.0
Breccia lava 14.76 0.25 1.40 47.8 0.6
Table 2. Mechanical properties of structural planes.
Structural planes Normal stiffness (GPa/m) Shear stiffness (GPa/m) Cohesion (MPa) Friction angle (°) Tensile strength (MPa)
Interlayer shear zones 0.2 0.074 0.09 15.6 0
Faults 3.0 1.000 0.15 26.0 0.05
Joints 10.0 6.000 0.25 35.0 0.20

3 IMPACT OF THE INTERLAYER SHEAR ZONE ON DEFORMATION MODE OF THE CAVERN SIDEWALL

Interlayer shear zone C2 is a large structural plane and crosses the axial line of the main caverns as shown in Figure 2. As the main concern in terms of stability of the underground project at the left bank, it definitely affects the sidewall deformation of the powerhouse cavern. In this case, numerical simulations were conducted with 3DEC to investigate the impact of the interlayer shear zone on the deformation mode of the cavern sidewall. The numerical simulations are vital to the subsequent cavern excavation, which can also guarantee safe construction.

3.1 Effect of the interlayer shear zone on sidewall deformation

When the initial maximum principal stress is horizontal, the deformation of the sidewall upstream is larger than that downstream. This is due to the height difference of vertical sidewall excavation. The numerical modeling conducted in 2011 during the basic design period shows that the interlayer shear zone obviously changed the deformation mode of the high sidewall (Figure 5). The interlayer shear zone C2 strikes the upstream. For the sidewall at the downstream side, C2 undergoes tensile shear deformation during excavation. This can cause large sidewall sliding along C2 toward the free face of the hanging wall. When C2 cuts the sidewall at a lower position, the deformation of the hanging wall at the downstream side reaches 125 mm (Figure 5a). In contrast, for the sidewall at the upstream side, C2 undergoes compressive shearing deformation during excavation and its shearing movement is quite small. When the layered zones are revealed after excavation, toppling deformation of the sidewall occurs at the footwall of C2 (Figure 5b). Thus, the large deformation of surrounding rocks at the upstream sidewall mainly exists in the footwall of the shallow part of C2. When C2 cuts the sidewall at a higher place, local deformation reaches up to 70–90 mm. Thus, this C2 causes a large difference in the discontinuous deformation at the upstream and the downstream sidewalls of this underground powerhouse cavern. It exerts a larger impact on the deformation difference of the downstream sidewall.

      Details are in the caption following the image          
Figure 5      
Open in figure viewer         PowerPoint      
Deformation mode of the upstream and downstream sidewalls of the powerhouse cavern affected by the interlayer shear zone. (a) Displacement distribution obtained by numerical analysis and (b) deformation mode of the high sidewall.

3.2 Deformation of the interlayer shear zone

The discontinuous deformation of the sidewall varies with the cutting height of the powerhouse cavern sidewall by the interlayer shear zone. Figure 6 shows the underground structure of the powerhouse cavern and eight conduits (named as unit 1 to unit 8) (Meng, Fan, et al., 2016). The interlayer shear zone strikes the upstream side, as shown in Figures 5b and 6. Shearing deformation of the interlayer shear zone is also different at the upstream and downstream sides and the shearing deformation of C2 is larger at the downstream sidewall than that at the upstream sidewall. Along the axis direction of the underground powerhouse cavern, the shearing deformation of C2 is larger at the south unit than at the north unit. The largest shearing deformation appears at the sidewall of units #2, #3, and #4 and the value is 60–70 mm. Furthermore, the shearing deformation in the interlayer shear zone is rather small and almost disappears as the distance from the powerhouse cavern exceeds the cavern width of 33.4 m.

      Details are in the caption following the image          
Figure 6      
Open in figure viewer         PowerPoint      
Shear deformation of interlayer shear zone C       2 along the axis of the powerhouse cavern (Meng, Fan, et al.,       2016).

3.3 Rock mechanical problems caused by the interlayer shear zone

The high sidewall of the underground powerhouse cavern undergoes strong stress relaxation. Being very soft in nature, the interlayer shear zone C2 becomes the moving boundary of the surrounding rocks under high stress conditions. If the rock masses above and below the interlayer shear zone are relatively intact, an overall shearing movement may occur at the hanging wall and footwall with overall stability. However, for rather fractured rock masses, the stress relaxation of the interlayer shear zone and the secondary structural plane may cause local stability in the rock masses.

The cavern axis orientation is N20° E. As shown by geological investigations, the angle between the major NWW joint set and the powerhouse axis is very large (Figure 1). Thus, large rock blocks will not be formed. However, the NE joint set may combine with C2 and the NWW joint set to form potential large deformation and unstable blocks. It should be noted that even though this study does not consider the creep effect, the creep of the interlayer shear zone containing clay may affect the long-term stability of the underground powerhouse cavern. In fact, the creep effect would be a good topic for future study.

4 CONTROL MEASURES FOR THE INTERLAYER SHEAR ZONE AND ITS EFFICIENCY EVALUATION

4.1 Comparison of tunnel-replacement schemes

A tunnel-replacement scheme was proposed to replace C2 with concrete. This control measure used is to reduce the shearing deformation of C2 and thus prevent severe unloading relaxation of the hanging wall and footwall of rock masses. The tunnels should not only control the shearing deformation of the interlayer shear zone but also ensure their safety. Under high in situ stresses, the key issue is the proper distance from the cavern sidewall to the replacement tunnels. If the replacement tunnels are too far away from the excavation face, shearing deformation can not be controlled effectively. If the replacement tunnels are too close to the excavation surface, the replacement tunnels may yield or even be cut off by the large shear stress. Thus, three replacement schemes were proposed during the detailed design stage in 2012. Concrete was used to fill in the tunnels in C2. The details of the plan and the corresponding effects are presented in Figure 7 and described as follows.

      Details are in the caption following the image          
Figure 7      
Open in figure viewer         PowerPoint      
Supporting effect on controlling shear deformation of interlayer shear zone C       2 when applying different replacement-tunnel schemes. (a) Deep replacement-tunnel scheme, (b) serial replacement-tunnel scheme, and (c) combination scheme.

Scheme 1 involves deep tunnel replacement. This scheme involves replacement of the interlayer shear zone 13–19 m away from the sidewall. As shown in Figure 7a, the deep shear deformation can be cut off effectively and systematically through this scheme. However, the shallow deformation is still large and the local shear deformation during excavation is 55–65 mm.

Scheme 2 involves serial tunnel replacement. This scheme involves replacement of the interlayer shear zone with serials of concrete tunnels perpendicular to the excavation surface. As shown in Figure 7b, this scheme can effectively control the shallow shear deformation along C2. However, the shear deformation between tunnels is still large and the local shear deformation during excavation is 50–60 mm.

Scheme 3 involves the combination of deep tunnel replacement, serial tunnel replacement, and concrete plug. Actually, this scheme is the combination of Scheme 1 and Scheme 2. As shown in Figure 7c, this scheme can reinforce both deep and shallow surrounding rocks at the same time. The local shear deformation of C2 during excavation can be significantly reduced to 20–30 mm. Therefore, Scheme 3 boasts of obvious advantages in deformation control.

4.2 Prediction of deformation of the sidewall and the interlayer shear zone in the construction stage

During the construction period, most of the underground excavation and support systems were determined. Although Scheme 3 was the most effective in controlling the shear deformation of the interlayer shear zone, it was difficult to ensure the safety of the concrete plug. In view of these considerations, the final control measure was a modified Scheme 3 that cancelled the concrete plug and reduced the spacing of serial tunnel replacement. The updated numerical simulations on the tunnel replacement of the interlayer shear zone were conducted in 2014. Both the surrounding rock deformation and the shear deformation of the interlayer shear zone C2 under high in situ stresses were predicted. The prediction results are presented below.

As shown in Figure 8, unloading deformation of the hanging wall of the interlayer shear zone around units #1–#5 is still large at the downstream side. The maximum displacement of the sidewall reaches up to 100–110 mm (Figure 8b). These places are in need of key reinforcement. Meanwhile, the largest shear deformation of the interlayer shear zone appears at around units #2–#4 at the downstream side of the powerhouse and could be reduced by 10–20 mm. The final largest shear deformation of C2 is 50–55 mm after tunnel replacement (Figure 9). However, shear displacement of the interlayer shear zone at the upstream side does not change much after tunnel replacement. This is inferred from the shear deformation of the interlayer shear zone around unit #3 (Figure 8b). Thus, replacement tunnels are not used in the interlayer shear zone at the upstream side.

      Details are in the caption following the image          
Figure 8      
Open in figure viewer         PowerPoint      
Deformation characteristics of the surrounding rocks of the powerhouse cavern after tunnel replacement. (a) Sidewall deformation at the upstream side and (b) sidewall deformation at the downstream side.
      Details are in the caption following the image          
Figure 9      
Open in figure viewer         PowerPoint      
Shearing deformation of the interlayer shear zone with and without replacement (based on the result of the vertical section across busbar tunnel #3). (a) Interlayer shear zone deformation without replacement and (b) interlayer shear zone deformation after replacement.

5 VERIFICATION OF THE NUMERICAL SIMULATIONS WITH SITE MONITORING DATA

5.1 Monitoring data on the deformation of surrounding rocks

The powerhouse cavern at the left bank is 438 m long, 34 m wide, and 88.7 m high. The excavation started from 2014 and lasted over 4 years up to 2018. The cavern was excavated in 10 stages, as shown in Figure 10. This excavation mode is called layered excavation. Each layer of excavation was conducted carefully and supported in a timely manner by strict analysis and double checking to prevent severe collapse. Figure 11 shows the photo of the powerhouse cavern taken at the site. The hanging wall sliding along C2 toward the free face, which is caused by tensile shear deformation of the shear zone, can be obviously seen on the sidewall at the downstream side (Figure 11a). This is a result of excavation and stress relief.

      Details are in the caption following the image          
Figure 10      
Open in figure viewer         PowerPoint      
Excavation stages of the powerhouse cavern.
      Details are in the caption following the image          
Figure 11      
Open in figure viewer         PowerPoint      
Powerhouse cavern and replacement tunnel. (a) Shearing movement of the hanging wall along the interlayer shear zone and (b) powerhouse cavern excavation at the left bank.

Monitoring instruments were installed in the construction stage. The extensometer Mzc0+042-1 was installed at the downstream sidewall of the powerhouse at the left bank, as shown in Figure 8b. The deformation of surrounding rock during and after the cavern excavation was monitored using an extensometer. Figure 12 presents the displacement at different distances of 0, 1.5, 4.5, 10.0, and 20.0 m away from the excavation face monitored from March 20, 2017 to March 15, 2020. The displacement of the sidewall was 75 mm on June 28, 2017. It can be seen that the deformation of the surrounding rocks increased quite rapidly during the first 3 months after the main powerhouse cavern was excavated from EL.575 m to EL.568 m. This was due to the strong stress relaxation after excavation stage VII. The displacement still increased rapidly after 3 months. It was 89.25 mm on the sidewall on August 19, 2017. The displacement of surrounding rock remained almost stable after July 2018. The final displacement of surrounding rocks was 105 mm at the excavation face and 25 mm at a distance of 20 m away from the excavation face. The displacement of surrounding rock 20 m away from the excavation face was smaller than 25 mm during the whole monitoring period. Both the predicted deformation of 110 mm in Figure 8 and the monitoring data from 2017 to 2020 (Figure 12) share similar change patterns. These site monitoring data verified the numerical simulation results of the surrounding rock deformations predicted earlier in 2012 (see Section 4.2).

      Details are in the caption following the image          
Figure 12      
Open in figure viewer         PowerPoint      
Surrounding rock displacement monitored by an extensometer Mzc0+042-1 at the downstream sidewall of the powerhouse at EL.575 m.

5.2 Data monitoring on shear deformation of the interlayer shear zone

In order to monitor shear deformation of the interlayer shear zone at the downstream side, a drilling hole with an inclinometer was set 6 meters away from the excavation face in busbar tunnel #3 in February 2017 (Figure 13a). The inclinometer INzmd3-0+023-1 captured successive and significant shear deformation in the process of layered excavation (Figure 13b). One month later, the monitored shear deformation was 13.5 mm on February 19, 2017. The largest shear deformation monitored was 52.91 mm on June 10, 2017. It took just 4 months for the shear zone to reach such a large shear deformation. Both the deformation pattern and the magnitude of deformation agree well with the numerical simulation results presented in Section 4.2 (Figure 9). Accordingly, it can be concluded that the deformation of the interlayer shear zone C2 and the underground powerhouse cavern during the construction stage can be predicted well using the numerical simulation procedure.

      Details are in the caption following the image          
Figure 13      
Open in figure viewer         PowerPoint      
Field monitoring. (a) Location of the inclinometer INzmd3-0+023-1 and (b) in situ monitoring data of shearing deformation of the interlayer shear zone obtained by the inclinometer in 2017.

6 LOCAL CRACKING MECHANISM OF THE REPLACEMENT TUNNELS

6.1 Effects of replacement tunnel location and replacement tunnel cracks

The location of replacement tunnels is a key parameter for controlling the shear deformation of the interlayer shear zone and the extent of rock mass stress relaxation. After many trials, replacement tunnels with a size of 6 m × 6 m were set 13 m away from the sidewall of the powerhouse cavern in the construction. This ensured that the replacement tunnels would not be completely cut even at places where large shearing deformation occurred.

The mechanical mechanism of deep replacement tunnels involves passing the shear loading along C2 from the hanging wall to the footwall of rock masses. As shown in Figure 14a, the shear stress inside the replacement tunnels increases during excavation of the cavern and the interlayer shear zone. After the interlayer shear zone is exposed, unloading relaxation of rock masses is induced at the footwall. Thus, the deformation difference between the hanging wall and the footwall becomes relatively small. The inclinometer readings show that shearing deformation decreases from 52.91 to 39.00 mm (Figure 13b). Therefore, shear loading of the replacement tunnels decreases in the meantime (Figure 14a). The shearing deformation along the interlayer shear zone is controlled and thus prompt anchoring is possible. However, replacement tunnels might still yield in this situation. Discontinuous cracks might occur in the concrete as well.

      Details are in the caption following the image          
Figure 14      
Open in figure viewer         PowerPoint      
Replacement tunnel. (a) Mechanical characteristics of the replacement tunnel at different excavation stages and (b) local cracks in the replacement tunnel caused by shear stress.

During layered excavation, cracks were actually observed in replacement tunnels in field investigations since they carried large loading of the surrounding rock masses and could yield at some places, as shown in Figure 14b. The distribution of unconnected cracks was consistent with that of shearing deformation of the interlayer shear zone and loading transport of replacement tunnels obtained in the numerical analysis. When the powerhouse cavern was further excavated to a lower altitude, the deformation of rock masses of the footwall would increase, and thus the shear deformation of the replacement tunnels would decrease.

6.2 Evaluation of replacement tunnel stability

The stability of replacement tunnels was evaluated using a strength reduction method (Liang et al., 2019). Specifically, the influence of fracture cracking and long-term stability of the replacement tunnels is determined by identifying the shearing deformation development of C2. Accordingly, it can be checked whether the replacement tunnels would undergo even more severe cracking or not. Numerical results show that the largest deformation still appears at the downstream sidewall from generator #2 to #4 during the strength reduction of tunnel concrete. As shown in Figure 15, when the strength reduction factor (SRF) is 3.0, the shearing deformation increment is smaller than 4 mm in the interlayer shear zone and smaller than 5 mm in the surrounding rocks; axial force increment of the bolt is smaller than 50 kN; and plastic zone and tensile stress zone increment is smaller than 1%.

      Details are in the caption following the image          
Figure 15      
Open in figure viewer         PowerPoint      
Shear deformation increase of the shear zone caused by strength reduction.

The replacement tunnel can play a very important role in transferring shearing loading from the hanging wall to the footwall. It would not go further cracking under such conditions. Even if it did, and even if the mechanical parameters of replacement tunnels decrease considerably, it would not cause a major change in sidewall deformation or the plastic deformation zone. It would not affect the anchoring system either. Therefore, the overall stability of the sidewall of the powerhouse cavern can be guaranteed.

7 CONCLUSIONS

Through geological investigations, field monitoring, and numerical simulations, a long-time tracking research was conducted on shearing deformation and control measures of the interlayer shear zone C   2 for the underground powerhouse cavern at the left bank of the Baihetan project. Based on the results obtained, the following conclusions can be drawn.
  • 1.

    Shearing deformation of interlayer shear zone C2 poses the key rock mechanical problem to the stability of underground powerhouse cavern at the left bank of the Baihetan hydropower plant. It changes the entire deformation mode of surrounding rock masses of the powerhouse cavern. The deformation of the downstream sidewall can reach 125 mm and shearing deformation of the interlayer shear zone can reach 60–70 mm.

  • 2.

    Deep replacement tunnel and series replacement-tunnel schemes can reduce the stress relaxation of the surrounding rocks of the powerhouse cavern. By reducing the maximum shearing deformation of the interlayer shear zone by 10–20 mm, this scheme can effectively control the potential risk caused by unfavorable geological conditions.

  • 3.

    Monitoring data in the construction period indicate that the deformation characteristics of the interlayer shear zone and surrounding rocks of the powerhouse cavern agree well with the numerical prediction in the detailed design period. The replacement-tunnel scheme for the interlayer shear zone is very effective. Replacement tunnels can transfer the loading in the hanging wall to the footwall, and thus restrain the shearing deformation along the interlayer shear zone. They can provide enough time for later fast anchoring support. During the excavation, the largest deformation in the surrounding rocks and the largest shearing deformation in the interlayer shear zone monitored are 105.50 and 52.91 mm, respectively, which agree well with the numerical simulation results obtained in the detailed design stage.

  • 4.

    Replacement tunnels yield in some places and unconnected cracks appear in the concrete. However, these will not induce failure of the surrounding rocks and the replacement tunnels. Replacement tunnels and the anchoring system can well restrain shearing deformation of the interlayer shear zone and rock mass stress relaxation. They ensure not only structural safety but also safety of rock masses. In all, they effectively mitigate the negative effect of interlayer shear zones on the high sidewall of the powerhouse cavern.

ACKNOWLEDGMENTS

This work was supported by the Program of China Three Gorges Corporation (BHT 0679-1).

    CONFLICT OF INTEREST STATEMENT

    The authors declare no conflict of interest.

    Biographies

    •       image      

      Dr. Lifang Zou works as a lab technician at the School of Earth Sciences and Engineering of Hohai University in China. She obtained her BSc and PhD degrees from Hohai University in 2005 and 2012, respectively. Her research mainly focuses on hydro–mechanical coupling of rocks. She has vast experience in laboratory experiments on mechanical properties and permeability of fractured rock masses, physical modeling of slope stability, and numerical simulations in geotechnical engineering. She has conducted considerable research on stability of slopes and deep underground excavations in hydropower projects.

    •       image      

      Dr. Guotao Meng works as a principal engineer in PowerChina Huadong Engineering Corporation, China. He obtained his BSc and MSc degrees from Kunming University of Science and Technology in 2001 and 2004, respectively. He received his PhD degree from Hohai University in 2007. He has over 17 years of experience in research and engineering applications related to civil engineering and mining. The scope of his work covers rock mass characterization, in situ stress assessment for the development of large-scale hydropower stations, theoretical and numerical study of the behavior of columnar basalt, and numerical modeling for various purposes, including verification of in situ tests on complex ground conditions, stability of rock slopes and underground excavations, and mechanisms of landslides. Dr. Meng has published two books and more than 40 papers.